Installation Guidelines for
the Adobe Unit
Step 1: Prepare the site

►
Dig a trench 16" wide for the full length of the wall you want to
construct. The depth of the trench should be between half of the unit's
height, and the full height of the unit.
► Place
leveling pad, consisting of a 2 to 3-inch layer of crushed stone or
gravel, over compacted soil.
Step 2: Set the base course

►
Once the leveling pad is complete, install the first layer of units. For
correct alignment, use a string line along the back to make sure they are
flush. Use a level to ensure the units are uniform front-to-back and
side-to-side.
► After
the base course is level and in place, backfill the void between and
behind the units with clean granular fill. It is important to tightly
compact the soil to ensure a soil base for the rest of the courses.
Step 3: Stack additional courses
► Before
placing the second course of units onto the base course, make sure the top
of the first layer of units is clean and is free of debris.
► Place
the next course onto the existing layer, backfill with dirt, and compact.
►
Repeat, placing additional courses of units until the desired height is
reached.
Special considerations

►
Sharp curves and half units will require cutting with a masonry cut-off
saw,* which can be rented at most equipment stores.
Unit dimensions: 6" high x 16" wide x 12" deep
*Follow instructions on proper usage
of equipment, and always wear your safety glasses and shoes.
|